After three weeks, the government presented the findings of a report Premier Body Control showing that the construction of roads and highways are delayed as construction companies do not have sufficient personnel and equipment, as contracts and work simultaneously on multiple sites.
Checks were conducted at the National Company of Motorways and National Roads, to identify the causes delays in execution of road infrastructure in progress, as verified period 1 January 2007 to 31 august 2012.
CNADNR recently terminated the contract for building the first section of Nadlac-Arad highway, mostly because of delayed works.
Also, CNADNR announced it will resume in January auction for the first section of Nadlac-Arad highway after termination of the association led by Romstrade company, owned by businessman Nelu Iordache, and estimated that the second section will be completed on time, respectively in April 2013.