Cernavoda NPP Unit 2 was restarted Friday morning after, after two days, the National Company Nuclearelectrica announced its downtime.

According to a press release Nuclearelectrica Unit 2 shutdown was caused by the erroneous acquisition by the plant process computer data entry to be entered into the computer periodically as routine activity.

The problem was repaired so that the unit currently works stable power.

"Nuclear safety personnel, population and environment was not affected at any time, all systems functioning as designed. Unplanned Despite this short stops, Cernavoda NPP Unit 2 remains in expected performance parameters for this year, so consumers will get Unit 2 record capacity factor (about 98%) since the beginning of commercial operation in 2007. Unit no. 2 remains therefore a central top global nuclear industry, "reads the communiqué Nuclearelectrica.

National Company Nuclearelectrica announced unplanned shutdown of Unit 2 of Cernavoda NPP Wednesday at 11.30. Unit automatically stopped due to unexpected triggering an automatic shutdown.